Diablo Canyon nuke plant could trigger higher PG&E customer bills

OAKLAND — Operation of the aging Diablo Canyon nuclear power plant — which has become a key element of California’s strained electricity grid — could shove PG&E monthly bills higher, some experts warn.

The Diablo Canyon nuclear energy complex, perched along a scenic stretch of the California coast in San Luis Obispo County, was scheduled to cease operations starting in 2025.

But when it turned out that California faced the forbidding prospect of electricity shortages without the nuclear plant, Gov. Gavin Newsom approved a law to keep the plant operating for years beyond its proposed retirement date.

Now, some experts estimate the costs of operating Diablo Canyon are rising far faster than originally thought, although PG&E says the latest estimates are inaccurate.

What appears clear, however, is that PG&E monthly bills could head higher as soon as early 2025 due to the costs of keeping the plant’s two nuclear reactors running.

Even PG&E anticipates higher bills, according to an April 2024 filing the utility submitted to the state Public Utilities Commission.

“PG&E’s allocated revenue requirement for the calendar year 2025 results in a $2.07 per month bill impact for the average non-CARE residential customer” due to the ongoing operation of Diablo Canyon, PG&E stated in the April 8 filing with the state PUC.

The state PUC has launched a proceeding that could culminate in a decision regarding how much PG&E can collect from its customers to bankroll Diablo Canyon’s operations over the next few years.

In May 2023, PG&E estimated it might cost $5.2 billion to operate Diablo Canyon from roughly 2025 through 2030, the first five years of the extended operations at the nuclear complex.

Yet by July 2023, that estimate had jumped 55.8% to a new figure of $8.1 billion over the five years.

“This is crazy and out of control,” said David Weisman, Alliance for Nuclear Responsibility executive director. “The costs continue to escalate for Diablo Canyon.”

Some experts, including those with the Alliance for Nuclear Responsibility advocacy group, believe the costs have reached $11.8 billion.

Oakland-based PG&E vehemently disputes the alliance’s assessment.

“The Alliance for Nuclear Responsibility, an anti-nuclear advocacy group, has incorrectly asserted that PG&E’s Diablo Canyon Power Plant extended operations forecast has grown to $11.8 billion,” PG&E stated in comments the company emailed to this news organization. “This assertion is false.”

Despite the dispute over the eventual aggregate costs to operate Diablo Canyon through 2030, what is certain is that the plant’s operation will add to already fast-rising PG&E monthly bills.

In January 2024, the average bill for the typical residential customer who doesn’t receive subsidies was $294.50 a month for those who receive combined electricity and gas services from PG&E.

FOLLOW US ON GOOGLE NEWS

Read original article here

Denial of responsibility! Chronicles Live is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – chronicleslive.com. The content will be deleted within 24 hours.